Mont Reve Progress Report - June 25

June 24, 2025

Mont Reve is nearing the end of its earthworks phase as we prepare to break ground on concrete foundations.

We are approximately two weeks away from reaching final depth with bulk earthworks now in the final stages. The remaining soil volume is being carefully trimmed and shaped to final levels. Natural lateral support installations are wrapping up, ensuring long-term stability of the excavated space.

Once complete, the final earth will be removed using a long-arm excavator, and the remaining support equipment will be craned out. From there, we will officially commence concrete foundation works in the basement—marking a significant milestone as we move into the structural phase of development.

The groundwork is nearly done. Now, we begin to build.

Watch June's Progress Report Below:

‍

‍

‍

‍

‍

‍

‍

‍



Previous post

Mont Reve Sales Day Vlog: A Sell-Out Success in Under an Hour

Next post

Atlantic Seaboard: Cape Town’s Premier Property Investment Destination in 2025​



STAY AHEAD OF THE MARKET

Subscribe to our newsletter for exclusive insights, expert real estate advice and BBG development updates

Contact Us

021 439 9030
info@bermanbros.co.za
‍
Suite 703, 7th Floor, The Point 76 Regent Rd
Sea Point, Cape Town

Mon - Fri: 08:00 - 16:00
Sat - Sun: Closed

HOME
About
DEVELOPMENTS
BLOG
CONTACT
© 2024 Berman Brothers Group,  All Rights Reserved 2024.