March 2, 2026

Mont Reve continues its upward momentum in February with another major milestone in the structural sequence. The team is casting pour one on the eighth floor, building on the completion of the sixth floor slab cast.
This progress reflects the disciplined corkscrew slab pour method that has defined the build from the start. Floor by floor, the structure rises in a controlled rhythm that supports both speed and accuracy. By locking alignment and tolerances into the concrete work early, follow on trades are able to move faster with fewer delays later.
With the sixth floor slab cast complete and the eighth floor now underway, Mont Reve is entering a phase where the building form becomes increasingly defined on the skyline. Each new pour is another step closer to the year end goal of completing the project with the quality standard that BBG is known for.
- Continue the eighth floor slab pours in sequence
- Maintain the corkscrew cycle to release areas for follow on trades
- Progress facade readiness in step with structural completion