Mont Reve

Mont Reve February 2026 Progress Update | Corkscrew pours push the build to level eight

March 2, 2026

Mont Reve continues its upward momentum in February with another major milestone in the structural sequence. The team is casting pour one on the eighth floor, building on the completion of the sixth floor slab cast.

This progress reflects the disciplined corkscrew slab pour method that has defined the build from the start. Floor by floor, the structure rises in a controlled rhythm that supports both speed and accuracy. By locking alignment and tolerances into the concrete work early, follow on trades are able to move faster with fewer delays later.

With the sixth floor slab cast complete and the eighth floor now underway, Mont Reve is entering a phase where the building form becomes increasingly defined on the skyline. Each new pour is another step closer to the year end goal of completing the project with the quality standard that BBG is known for.

‍

Watch The Progression

‍

‍

What is next

- Continue the eighth floor slab pours in sequence
- Maintain the corkscrew cycle to release areas for follow on trades
- Progress facade readiness in step with structural completion

‍

‍

‍

‍

‍



Previous post

Do You Need Full Capital Upfront When Buying Property?

Next post

Behind The Design with Architect Robert Silke: Mont Reve



STAY AHEAD OF THE MARKET

Subscribe to our newsletter for exclusive insights, expert real estate advice and BBG development updates

Contact Us

021 439 9030
info@bermanbros.co.za
‍
Suite 703, 7th Floor, The Point 76 Regent Rd
Sea Point, Cape Town

Mon - Fri: 08:00 - 16:00
Sat - Sun: Closed

HOME
About
DEVELOPMENTS
BLOG
CONTACT
© 2025 Berman Brothers Group,  All Rights Reserved.